Project Updates
Work Scheduled within the next two weeks
- On-going construction items.
- Finish cable tray.
- Ceiling grid on-going.
- Start ceramic tile.
- Insulate VAV's.
- Finish ceiling rough-ins.
- First finish coat on all painted surfaces.
- Miscellaneous MPR ceiling framing on-going.
- Roof screen metal installation after snow melts from roof.
- Bay window installed.
- Cap north curtain wall.
- Finish installation of storefronts.
- Finish cable tray, possibly 3 weeks.
- Set store fronts, possibly start glazing.
- Prime second floor.
- Start second floor ceiling grid.
- Start ceramic tile in restrooms.
- Final louvers delivered.
- Start and finish MPR ceiling grid.
Summary of Work Completed
3/9/10
- Building has been enclosed, curtain wall almost installed.
- Miscellaneous framing almost done, vestibules on-going.
- Drywall loose-ends on-going.
- Mechanical rough-ins almost complete.
- Plumbing rough-ins complete, VAV's almost complete.
- Roof scuppers at stairwells on-going, still need to be trimmed and flashed.
- Parapet is flashed but not sealed.
- Grass pavers almost done (up to radius). Sod pending weather.
- Conduit rough-in ongoing.
- Primary masonry complete, precise coping on-going.
- Remaining pieces have been ordered.
- Aluminum composite panel prep work on-going.
- Precast repairs ongoing, currently on hold due to weather and new concrete.
- Overhead door installed.
- Curtain wall installation almost complete.
- CW caps on-going.
- CW trim on-going.
- Roof top units have been set.
- First and second floor ceiling grid on-going.
- Second floor cable tray started.
- Ceramic tile has started in the restrooms.
- MEP Field Report items on-going.
- Drywall priming on-going.
2/23/10
- Building has been enclosed, curtain wall almost completely installed.
- Miscellaneous framing almost done, vestibules on-going.
- Drywall loose-ends on-going.
- Mechanical rough-ins almost complete.
- Plumbing rough-ins complete, VAV's almost complete.
- Roof scuppers at stairwells on-going, still need to be trimmed and flashed.
- Parapet is flashed but not sealed.
- Grass pavers almost done (up to radius). Sod pending weather.
- Conduit rough-in on-going.
- Primary masonry complete, precast coping on-going.
- Remaining pieces have been ordered
- Aluminum composite panel prep work on-going.
- Precast repairs ongoing, currently on hold due to weather and new concrete.
- Overhead door installed.
- Curtain wall installation almost complete.
- CW caps on-going
- CW trim on-going
- Roof top units have been set.
- First and second floor ceiling grid started.
1/25/10
- Building has been enclosed, with most of the curtain wall installed and some plywood infill closing other areas.
- Miscellaneous interior ceiling framing almost done.
- Mechanical rough-ins almost complete.
- Plumbing rough-ins complete, VAV's almost complete.
- Roof scuppers at stairwells on-going.
- Parapet is flashed.
- Grass pavers almost done (up to radius). Sod pending weather.
- Bulletin 017 modifications completed.
- Conduit rough-in-on-going.
- Primary masonry complete, precast coping ongoing.
- Roofing membrane complete, including canopies.
- Aluminum composite panel prep work has started.
- Precast repairs ongoing, currently on hold due to weather.
- Overhead door installed.
- Curtain wall installation on going
- LCW-1's installed and sealed, with caps.
- Southern curtain wall is complete, not including doors.
12/22/09
- Interior ceiling framing on-going in lobby, vending, and vestibule areas.
- MEP rough-in almost complete.
- Bulletin 017 modifications mostly completed.
- Storm water management pond expansion and pond below gravel lot are substantially complete. A minor check dam repair is still required.
- Conduit rough-in ongoing.
- Primary masonry almost complete, flashing and veneer modifications being finalized.
- Plumbing roughed in (not including VAV's).
- Roofing membrane almost complete.
- Aluminum composite panel prep work has started.
- Precast repairs ongoing.
- Curtainwall installation started.
11/9/09
- Steel has been completed. Stairs and Catwalks ongoing.
- MEP rough-in ongoing.
- Roof screens installation framed.
- Exterior framing completed.
- Exterior sheathing and insulation complete, including 5" extension.
- Interior ceiling framing on-going in lobby areas and vestibule areas.
- Bulletin 017 modifications pending.
- Storm water management pond expansion and pond below gravel lot are substantially complete.
- Conduit rough-in on-going.
- Mechanical rough-ins ongoing.
- Stairwell masonry almost complete.
- Primary masonry started.
- Plumber started running copper lines up high.
- Roofing membrane almost complete, exempting recent RFI areas.
10/13/09
- Plumbing, ducts, rain leaders ongoing.
- Roof screens installation framed.
- Exterior framing completed.
- Exterior sheathing and insulation almost complete.
- Interior framing ongoing; area between column lines A-C is 90% complete, Multipurpose Room framing 50% complete.
- Storm water management pond expansion and pond below gravel lot are almost complete.
- Conduit rough-in on going.
- Mechanical rough-ins ongoing.
- Removed majority of unsatisfactory brick from west side.
- Stairwell masonry ongoing.
- Roofing started, 45% complete.
Archived Updates
9/3/09
- Steel has been completed, not including stairs, catwalks.
- Parapet framing completed.
- Plumbing, ducts, rain leaders ongoing.
- Roof screens installation ongoing.
- Exterior framing completed.
- Exterior sheathing and insulation ongoing.
- Interior framing ongoing: First floor 50% complete, Second floor 90% complete.
- Storm water management pond expansion and pond below gravel lot are almost complete.
- Conduit on-going.
- Mechanical rough-ins ongoing.
- Exterior brick masonry started.
8/25/09
- 95% of the steel has been completed, not including stairs, catwalks.
- Multipurpose room steel has been erected.
- Canopy decking started.
- Roof screens installation has started.
- Exterior framing ongoing.
- Exterior sheathing ongoing.
- Interior framing has started.
- Storm water management pond expansion and pond below gravel lot are almost complete.
- Started 8" sanitary line complete to main. Yard inles are in and connected to storm line.
- Plumbing in un-poured areas.
- Conduit started.
- Kickers and steel decking has started.
7/28/09
- Steel erected on rectangular portion of building completed.
- Multipurpose room steel has been erected.
- Canopy steel started.
- Roof screens delivered and installation has started.
- Exterior framing started.
- Exterior sheathing started.
- Second floor slab poured.
- Storm water management pond expansion and pond below gravel lot are almost complete.
- Started 8" sanitary line.
- Most first floor diamonds have been poured.
6/24/09
- Half of first floor slab on grade poured
- Masonry work on-going
- North Stair rebuilt
- South stairwell done
- Plumbing roughed-in to Warming Pantry
- Damp-proofing has been started on the foundation wall
- Pond enlargement started
- Gravel lot on-going. Work will be done at a more rapid pace after the steel erection begins
4/28/09
- Footings at north end started.
- Ductbank into building.
- Perimeter insulation.
- Formed north corner slab.
4/14/09
- Light pole bases poured.
- Landscaping complete at gravel lot.
- Alson H. Smith Jr. Technology Center sidewalk poured to north corner.
- Building footings started.
3/24/09
- Storm at east side of building is complete.
- Dumpster pad installed.
- Data duct installed up to service road.
- Light poles excavated and conduit installed.
2/24/09
- Sanitary lines installed.
- Fire connection of Alson H. Smith Jr., Technology Building.
- Curb and gutter at gravel lot.
- 8" and 4" wet taps.
- Pond on grade at 90%.
- Seeding dam and pond embankment.
2/10/09
- Sanitary lines staked out.
- Gravel lot structures set. 15" O.C. between structures1 & 2. Tied into existing structures.
- Water main A and fire line E – Tested and approved by fire marshal.
1/27/09
- SWM pond burm at grade.
- Pond work at 98% completion.
- Modifications to structures complete.
- DCR was on site yesterday – Pleased with work completed to date.
- Site utility contractor onsite – Starting on water line.
- Primary and secondary conduit in – Primary runs to transformer; while secondary runs to building
- Pole bases poured.
1/13/09
- POND: Cutoff wall is poured. Stake out complete.
- Asphalt/ curb and gutter – removed / demoed
- Site Utility Contractor - Start next week.
- Footings – Rebar on site.
- Gravel Lot – Being used as side work (Filler).
12/9/08
- Trailers set up
- Fencing - Install tomorrow
- Construction entrance started – Info sent to VDOT
- Gravel lot started
11/25/2008
- Mobilized, Setting up E & S Controls.