Project Updates

Work Scheduled within the next two weeks

  • Ongoing construction items.
  • Roof material delivery next Wednesday.
  • Stairwell masonry.
  • Site concrete preparation, pour scheduled week of 21st.

Summary of Work Completed

9/3/09

  • Steel has been completed, not including stairs, catwalks.
  • Parapet framing completed.
  • Plumbing, ducts, rain leaders ongoing.
  • Roof screens installation ongoing.
  • Exterior framing completed.
  • Exterior sheathing and insulation ongoing.
  • Interior framing ongoing: First floor 50% complete, Second floor 90% complete.
  • Storm water management pond expansion and pond below gravel lot are almost complete.
  • Conduit on-going.
  • Mechanical rough-ins ongoing.
  • Exterior brick masonry started.

8/25/09

  • 95% of the steel has been completed, not including stairs, catwalks.
  • Multipurpose room steel has been erected.
  • Canopy decking started.
  • Roof screens installation has started.
  • Exterior framing ongoing.
  • Exterior sheathing ongoing.
  • Interior framing has started.
  • Storm water management pond expansion and pond below gravel lot are almost complete.
  • Started 8" sanitary line complete to main.  Yard inles are in and connected to storm line.
  • Plumbing in un-poured areas.
  • Conduit started.
  • Kickers and steel decking has started.

7/28/09

  • Steel erected on rectangular portion of building completed.
  • Multipurpose room steel has been erected.
  • Canopy steel started.
  • Roof screens delivered and installation has started.
  • Exterior framing started.
  • Exterior sheathing started.
  • Second floor slab poured.
  • Storm water management pond expansion and pond below gravel lot are almost complete.
  • Started 8" sanitary line.
  • Most first floor diamonds have been poured.

6/24/09

  • Half of first floor slab on grade poured
  • Masonry work on-going
  • North Stair rebuilt
  • South stairwell done
  • Plumbing roughed-in to Warming Pantry
  • Damp-proofing has been started on the foundation wall
  • Pond enlargement started
  • Gravel lot on-going. Work will be done at a more rapid pace after the steel erection begins

4/28/09

  • Footings at north end started.
  • Ductbank into building.
  • Perimeter insulation.
  • Formed north corner slab.

4/14/09

  • Light pole bases poured.
  • Landscaping complete at gravel lot.
  • Alson H. Smith Jr. Technology Center sidewalk poured to north corner.
  • Building footings started.